Drivers of Delays in Infrastructure Procurement
Infrastructure procurement delays are widespread, with nearly 44% of World Bank contracts experiencing significant delays between actual and planned contract sign dates. Delays are primarily caused by:
Key Findings
-
Procurement Stages:
- The evaluation period (bid or prequalification evaluation) is the most frequent stage experiencing delays across all procurement methods.
- Single-stage, single-envelope tenders saw the longest average contract signature delays among all methods.
-
Proposed Changes:
- Project Preparation: Investing in site surveys and complete designs reduces the likelihood of delays during later stages.
- Contract Framework: Implementing adaptable contracts with proper procurement methods managed at the outset reduces procurement risks.
- Financing: Prioritizing regular budget approval and cash flow ensures timely project execution.
-
Capacity and Governance:
- Strengthening institutional procurement capacity and promoting transparent, digital procurement systems can significantly reduce delays.
Summary of Key Points
- Over 40% of infrastructure projects face procurement and contract execution delays.
- Key drivers include weak institutional capacity, poor project preparation, funding constraints, and environmental factors.
- Recommendations focus on capacity building, preventative risk measures, and the adoption of e-government procurement systems.
This report underscores the need for systematic reforms in infrastructure project procurement to mitigate delays and improve outcomes.