Report Summary: Building a GB electricity network ready for net zero
Introduction to the Challenge
- Key Goal: Achieve net zero by 2050, decarbonizing the electricity system by 2035.
- Grid Challenges:
- Consumer Electrification: Transition to EVs and heat pumps will surge electricity demand, requiring upgrades to low-voltage distribution networks. Current headroom averages 60%, with potential shortfalls by 2035.
- Renewable Integration: Long connection lead times (over 15 years for transmission) delay gigawatt-scale renewable projects.
- Transmission Constraints: Offshore wind target (50GW by 2030) requires urgent investment in transmission capacity, exacerbated by supply chain and consenting bottlenecks.
Key Recommendations
-
Distribution Networks:
- Strategic investment and digitalization to accelerate reinforcement and manage demand-side flexibility (EV smart charging, heat pump upgrades).
- Government must commit to electrifying heat and transport to enable network planning.
-
Transmission-Distribution Interface:
- Reform connections process for queue management, prioritizing low-carbon projects.
- Streamline transmission-distribution coordination to avoid excessive impact assessments.
-
Transmission Networks:
- Establish the Future System Operator (FSO) with a clear timeline to coordinate strategic transmission investment.
- Accelerate supply chains and consenting for projects, avoiding delays in critical large-scale infrastructure.
Economic and Strategic Importance
- Innovation & Investment: A £70-140bn net-zero-ready grid investment could lower unit electricity costs despite rising totals, unlocking economic opportunities (e.g., 50k-130k+ jobs).
- Energy Export Potential: Aiming for net energy exports by 2040 reduces vulnerability to global energy markets.
- Policy Imperatives: Urgent delivery is needed to avoid constraint costs (e.g., £1.2bn in 2022) and geopolitical risks.
Initiatives and Progress
- Near-Term Actions:
- GB Connections Reform to modernize connection processes.
- Ofgem’s shift to “Invest and Connect” framework, with ASTI (Accelerated Strategic Transmission Investment) framework.
- Ongoing Challenges:
- Supply chain shortages and delayed transmission consents risk project timelines.
- Ofgem’s Distributor Investment Regulation gamble may limit network capacity.
Data Points:
- Connection Traffic: 2023 transmission applications exceed 2018 total, signaling massive project pipeline.
- Capacity Goals: 180-220GW low-carbon capacity needed by 2035, an average of 6-9GW/year, up from historical rates.